2023 Public Works’ Road Work Plan
Read Below for the Updated 2023 Public Works Department Roads Plan:
ROADS DEPARTMENT
WORK PLAN FOR 2023
*******************************************************************
Colonization Rd
Drive way culvert
B gravel 30 yards
Gordon Lake Rd
Resurfacing from Suddaby Park to McKinnon Side Rd
Rip 2.8 km of old surface treatment
2 km ditching
2 cross culverts
Filter cloth
Grade raise between first and second bridge 30 loads B
Cap 2.8 km with A gravel
Old Soo Rd at Bell Pole 12
Change 1200 mm cross culvert
Grade raise over culvert
400 yards B gravel
Cap with A gravel
600 m ditching
Government Rd
Cross pipe just west of Fisher Rd, 75 yards B gravel
Cross pipe just east of Fisher Rd, 25 yards B gravel
A gravel for both 50 yards
Maintenance Gravel
25 Yard loads
10 loads Desbarats lake Rd
4 loads McClelland road E
10 loads Fisher Rd Gordon Lake Rd to Government
20 loads Fisher Rd, Deplonty to Hwy 17
10 loads Government Rd, Gordon Lake Rd to Fisher Rd
20 loads Government Rd, Fisher Rd to Twp boundary
2 loads Lantern Lane
10 loads McKinnon side Rd
Ditching
Carter Side Rd 500m
Desbarats Lake Rd 200m
McKinnon side Rd 400m
Fisher Rd south of Deplonty 400m
Cora Dr
200m brushing
300m ditching
Install 2400mm x 20 m culvert
15 loads B gravel
15 loads A gravel
– Road side grass cutting
– Grading
– Dust control [calcium]
– Haul Sediment from lagoons to landfill
– Excavation work for office addition
– Landscape and construct entrance to Arena / North End
– Landscape for drainage around Arena
– Road patching
– Road Asset Plan Assessment
– Fence Lot Addition to Garage property
– Replace culvert in Lagoon driveway
– Prep site for Sand Shed construction